South Rail Systems Alliance (SRSA) carried out the largest deployment of geofencing devices to date to support a complex 12-day S&C renewal blockade at Dolphin Junction in Slough. Delivered in partnership with RSS Infrastructure (RSSI), Tended’s system was deployed in a highly dynamic rail environment where possession limits changed daily, increasing the risk of inadvertent movement onto open rail lines.
Objectives
- Ensure the safe management of workforce and asset movements amid daily changes to possession limits
- Minimise the risk of inadvertent access to open lines during possession changes
- Reduce the risk of incorrect use of access and egress routes
- Decrease reliance on briefings and manual controls in a high-risk environment
- Support SRSA in delivering the renewal safely, efficiently, and on schedule